0.2.1-1

Demolition of entire buildings

Unit: m2 Sub-Element: 0.2.1 - Demolition works
Component Information
Code:
0.2.1-1
Sequence:
1
Unit:
m2
Sub-Element:
0.2.1 - Demolition works
Description:

Demolition of entire buildings

Details to State:

details to be stated

Component Statistics
4
Measurement Rules
10
Included Items
7
Excluded Items
Measurement Rules (4)
C1 1

Where components are to be enumerated, the number of components is to be stated.

C2 2

The linear length of components is measured on the centre line of the component.

C3 3

The area measured is the GEFA.

C4 4

Other cost-significant components are to be described and identified separately. Such components are to be measured by area (m2) or linear measurement (m), or enumerated (nr) separately

Included Items (10)
1.

Demolition of entire buildings and structures, including removing service installations (i.e. significant buildings and structures).

2.

Demolition of major parts of existing buildings and structures (including removing service installations) ready to receive new construction.

3.

Credits for materials arising from demolition works.

4.

Disposal of materials arising from demolition, including materials classified as inert, non-hazardous and hazardous (including WAC (waste acceptance criteria) test charges).

5.

Disconnecting existing mains services, including water, gas, electricity, drainage, district heating, telecommunication systems, data systems, etc.).

6.

Statutory undertaker’s fees and charges for disconnecting mains services.

7.

Temporary supports to retain existing basement retaining walls, etc., including the design, installation, maintenance, repositioning (to facilitate construction works) and removal of props and wailings, and grubbing up and disposal of anchor blocks/foundations where not part of the permanent works.

8.

Periodic temporary inspections.

9.

Sundry items.

10.

Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.

Excluded Items (7)
1.

Soft strip works carried out separately from demolition works.

2. Ref: 7

Removing parts of existing buildings (included in group element 7).

3. Ref: 7

Alterations to existing buildings (included in group element 7).

4. Ref: 7.1.1

Stripping out services in conjunction with alteration works to existing buildings (included in sub-element 7.1.1).

5. Ref: 0.1.1

Decontaminating existing service systems prior to demolition,e.g. boilers and fuel storage tanks and vessels (included in sub-element 0.1.1).

6. Ref: 7.4

Temporary or semi-permanent support to structures or facades (included in element 7.4).

7. Ref: 8.1.1

Minor demolitions carried out as part of the site clearance (included in sub-element 8.1.1).

Export
View as JSON
API Access