9 GroupsTop-level categories in the NRM1 construction classification system. Each group contains multiple elements that further break down into sub-elements and components.
0 Facilitating works
Works associated with general site preparation and groundworks
Elements
1 Substructure
Group Element 1 comprises structural elements below ground level, including foundations, basement construction, and associated drainage installations.
Elements
2 Superstructure
Group element 2 comprises structural and enclosing elements above ground level
Elements
3 Internal finishes
Group Element 3 comprises internal and external surface finishes, including wall, floor, and ceiling finishes that provide the final appearance and protection to the building surfaces.
Elements
4 Fittings, furnishings and equipment
Group Element 4 comprises fittings, furnishings, and equipment that complete the building’s functional and aesthetic requirements, including items fixed or loose that support the intended use of the facility.
Elements
5 Services
Group Element 5 comprises all building services installations necessary for the operation and comfort of the facility. These include sanitary, water, disposal, heating, ventilation, air conditioning, electrical, and communication systems, as well as lifts, fire protection, and specialist installations. It also covers builder’s work associated with these services. The element includes provisions for testing, commissioning, and initial operation of all mechanical and electrical systems to ensure full functionality and compliance with performance requirements.
Elements
6 Prefabricated buildings and building units
Group Element 6 comprises prefabricated buildings and building units that are manufactured off-site and assembled on-site. It includes provisions for testing, commissioning, and initial operation to ensure that all systems and installations meet performance and operational requirements upon completion.
Elements
7 Work to existing buildings
Group Element 7 comprises works associated with existing buildings, including minor demolition, alterations, repairs to services, damp-proofing, facade retention, cleaning, and renovation activities. It covers restoration and improvement works necessary to maintain or upgrade existing structures, excluding fit-out works for new buildings, which are measured separately as new construction.
Elements
8 External works
Group Element 8 comprises external works and landscaping associated with the completed building. It includes site preparation, roads, paths, pavings, soft landscaping, fencing, external fixtures, drainage, and services, as well as minor ancillary buildings. Works involving hazardous material removal, major demolition, or specialist groundworks are excluded and measured under Group Element 0.