7.6.5-1

Plastics repairs

Unit: nr/m/m2 Sub-Element: 7.6.5 - Plastics repairs
Component Information
Code:
7.6.5-1
Sequence:
1
Unit:
nr/m/m2
Sub-Element:
7.6.5 - Plastics repairs
Description:

Plastics repairs

Details to State:

details to be stated

Component Statistics
4
Measurement Rules
5
Included Items
1
Excluded Items
Measurement Rules (4)
C1 1

Where components are to be enumerated, the number of components is to be stated.

C3 1

The area measured is the surface area of the repair.

C2 2

The length of linear components measured is their extreme length,over all obstructions.

C4 4

Work arising out of party wall awards/agreements is to be described and identified separately.

Included Items (5)
1.

Renewing domed rooflights.

2.

Overhauling of windows, rooflights, doors, etc.

3.

Repairs to rooflights, doors, etc.

4.

Sundry items.

5.

Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.

Excluded Items (1)
1. Ref: 7.1.1

Renewing/replacing plastic items in their entirety, e.g. roof coverings, windows, doors (including frames), rooflights, etc. (included in group element 2 or sub-element 7.1.1, as appropriate).