6.1.2-1
Prefabricated room units,including type of unit, GIFA of unit (in m2 ), construction of unit and content of units, to be stated.
Component Information
- Code:
- 6.1.2-1
- Sequence:
- 1
- Unit:
- m2
- Sub-Element:
- 6.1.2 - 2 Building units
Prefabricated room units,including type of unit, GIFA of unit (in m2 ), construction of unit and content of units, to be stated.
Component Statistics
Measurement Rules
Included Items
Excluded Items
Measurement Rules (5)
Where components are to be enumerated, the number of components is to be stated.
The area measured is the GIFA for each type of unit.
Building units of different type, composition and GIFA are to be measured separately.
Where the contractor is only responsible for designing specific elements and/or components of the building project (i.e. not the entire building project), contractor-designed work is to be described and identified separately
The percentage additions for testing and commissioning are to be applied to the total cost of the items comprising the sub-element. A single combined percentage addition can be applied to cover the costs of both testing and commissioning.
Included Items (6)
1 Prefabricated modular room units, singular or multiple, which are to be enclosed by an external envelope, such as: • accommodation units/bedroom units • hotel suites • office units • classrooms • toilet units/washroom units • corridors • staircases • student accommodation • soundproof rooms • computer rooms cold rooms • spray booths • kitchens • kiosks • healthcare modules, including operating theatres.
Where included as part of the building unit: • structure, roof and wall cladding • windows, external doors,stairs, etc. • internal partitions, linings and finishes • internal doors • fixtures, furnishings and equipment • sanitary appliances • mechanical and electrical services • stopping up and sealing holes • fire-resistant stopping, including fire sleeves • fire breaks around units.
Final connections of cold water, hot water, electricity and other fuels to pods
Sundry items.
Testing and commissioning.
Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.
Excluded Items (2)
Complete self-finished prefabricated modular buildings (included in sub-element 6.1.1).
Bathroom, toilet and shower pods, supplied as completed units, manufactured off-site (included in sub-element 6.1.3)