5.9.2-1

Piped distribution systems

Unit: m2 Sub-Element: 5.9.2 - 2 Fuel distribution systems
Component Information
Code:
5.9.2-1
Sequence:
1
Unit:
m2
Sub-Element:
5.9.2 - 2 Fuel distribution systems
Description:

Piped distribution systems

Details to State:

details to be stated

Component Statistics
5
Measurement Rules
12
Included Items
4
Excluded Items
Measurement Rules (5)
C1 1

The area measured is the total GIFA of the building.

C2 2

Installations for residential units, hotel rooms, student accommodation units, etc. may be enumerated (nr). The type of residential unit or room, and size (by number of bedrooms) of unit, is to be stated.

C3 3

Work to existing buildings is to be described and identified separately.

C4 4

Where the contractor is only responsible for designing specific elements and/or components of the building project (i.e. not the entire building project), contractor-designed work is to be described and identified separately.

C5 5

The percentage additions for testing and commissioning are to be applied to the total cost of the items comprising the sub-element. A single combined percentage addition can be applied to cover the costs of both testing and commissioning.

Included Items (12)
1.

Gas, oil, petrol, diesel and LPG, and other fuel systems.

2.

Distribution pipelines from mains connection point within building to user points, including pipeline ancillaries and fittings.

3.

Pipeline components/ancillaries (e.g. valves and pumps).

4.

Bracketry.

5.

Manifolds, local meters, gas governors, gas boosters and gas connection outlets.

6.

Terminal control equipment.

7.

Thermal insulation.

8.

Off-site painting/anti-corrosion treatments.

9.

Monitoring equipment.

10.

Sundry items.

11.

Testing and commissioning.

12.

Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.

Excluded Items (4)
1. Ref: 8.7.5

Connection to the statutory undertaker’s main (included in sub-element 8.7.5).

2. Ref: 5.14

On-site painting of pipelines and supports for pipelines (included in element 5.14).

3. Ref: 5.12.3

Building management systems and other control systems (included in sub-element 5.12.3).

4. Ref: 5.14

Builder’s work in connection with services (included in element 5.14).