5.3.3-1
Refuse disposal installations
Component Information
- Code:
- 5.3.3-1
- Sequence:
- 1
- Unit:
- nr
- Sub-Element:
- 5.3.3 - 3 Refuse disposal
Refuse disposal installations
details to be stated
Component Statistics
Measurement Rules
Included Items
Excluded Items
Measurement Rules (4)
Where components are to be enumerated, the number of components is to be stated.
Work to existing buildings is to be described and identified separately.
Where the contractor is only responsible for designing specific elements and/or components of the building project (i.e. not the entire building project), contractor-designed work is to be described and identified separately.
The percentage additions for testing and commissioning are to be applied to the total cost of the items comprising the sub-element. A single combined percentage addition can be applied to cover the costs of both testing and commissioning.
Included Items (12)
Refuse input devices.
Refuse chutes and ducts.
Plant for the compacting/macerating of refuse ready for collection (including compactors, bailing machines and shredding machines).
Refuse collection equipment, including bins and continental bins.
Incineration plant and ancillaries, including refuse and waste-handling equipment, afterburners, proprietary metal chimney and flues, and ash-handling equipment, as well as gas-fired incineration plant.
Paper shredders.
Safety devices.
Painting/anti-corrosive treatments.
Final connections to services.
Sundry items.
Testing and commissioning.
Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.
Excluded Items (2)
Sanitary incinerators and sanitary macerators (included in sub-element 5.1.2).
Builder’s work in connection with services (included in element 5.14).