5.13.2-1

Cold rooms

Unit: nr/m2 Sub-Element: 5.13.2 - 2 Specialist refrigeration systems
Component Information
Code:
5.13.2-1
Sequence:
1
Unit:
nr/m2
Sub-Element:
5.13.2 - 2 Specialist refrigeration systems
Description:

Cold rooms

Details to State:

details of each type of system to be stated.

Component Statistics
6
Measurement Rules
6
Included Items
6
Excluded Items
Measurement Rules (6)
C1 1

Where components are to be enumerated, the number of components is to be stated.

C2 2

The area measured is the area serviced by the system (i.e. the area of the rooms and circulation spaces that are served by the system, which is not necessarily the total GIFA of the building). The area serviced is measured using the rules of measurement for ascertaining the GIFA.

C3 3

Where more than one system is employed, the area measured for each system is the area serviced by the system.

C4 4

Work to existing buildings is to be described and identified separately.

C5 5

Where the contractor is only responsible for designing specific elements and/or components of the building project (i.e. not the entire building project), contractor-designed work is to be described and identified separately.

C6 6

The percentage additions for testing and commissioning are to be applied to the total cost of the items comprising the sub-element. A single combined percentage addition can be applied to cover the costs of both testing and commissioning.

Included Items (6)
1.

Cold rooms, including packaged cold rooms, packaged walk-in freezers, wall panels and linings, ceiling panels and linings, flooring systems, doors and door mechanisms, jointing material, thermal cladding, refrigeration plant and equipment, evaporators, lighting, etc.

2.

Ice pads, including waterproof layer, insulation layer, working screed, slip plane layer, bonded refrigeration pads (incorporating pipelines, reinforcement, etc.), floor drains and sealing plates, cooling towers, evaporative condensers, heat recovery systems, etc.

3.

Other specialist refrigeration systems.

4.

Sundry items.

5.

Testing and commissioning.

6.

Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.

Excluded Items (6)
1. Ref: 5.6.3

Central refrigeration plant and chillers (included in sub-element 5.6.3).

2. Ref: 5.6.3

Cooling towers (included in sub-element 5.6.3).

3. Ref: 8.8.2

External cooling towers (included in sub-element 8.8.2).

4. Ref: 5.8.2

General-purpose LV power supplies (included in sub-element 5.8.2).

5. Ref: 5.12.3

Building management systems and other control systems (included in sub-element 5.12.3).

6. Ref: 5.14

Builder’s work in connection with services (included in element 5.14).