5.13.1-1
Medical and laboratory gas supply systems
Component Information
- Code:
- 5.13.1-1
- Sequence:
- 1
- Unit:
- nr/m2
- Sub-Element:
- 5.13.1 - 1 Specialist piped supply installations
Medical and laboratory gas supply systems
details of each type of system to be stated.
Component Statistics
Measurement Rules
Included Items
Excluded Items
Measurement Rules (6)
Where components are to be enumerated, the number of components is to be stated.
The area measured is the area serviced by the system (i.e. the area of the rooms and circulation spaces that are served by the system, which is not necessarily the total GIFA of the building). The area serviced is measured using the rules of measurement for ascertaining the GIFA.
Where more than one system is employed, the area measured for each system is the area serviced by the system.
Work to existing buildings is to be described and identified separately.
Where the contractor is only responsible for designing specific elements and/or components of the building project (i.e. not the entire building project), contractor-designed work is to be described and identified separately.
The percentage additions for testing and commissioning are to be applied to the total cost of the items comprising the sub-element. A single combined percentage addition can be applied to cover the costs of both testing and commissioning.
Included Items (15)
Medical and laboratory gas supply systems, including gas bottles and bulk storage vessels, manifold headers, gas governors, monitoring equipment, terminal control equipment, gas detection and alarm equipment, gas connection outlets, etc.
Centralised vacuum cleaning systems, including vacuum pumps, blowers and vacuum connection units.
Treated water systems, including de-alkalisation, de-ionisation, de-aeration, raw sewage storage tanks and vessels, chemical storage tanks and vessels, purified water tanks and vessels, distillation equipment, electrolytic chlorine ion generation equipment, demineralisation plant, reverse osmosis plant, etc.
Swimming pool water treatment, including filter vessels, chemical storage vessels, chemical dosing equipment, ozone generation and injection equipment, de-ozoning vessels, electrolytic chlorine ion generation equipment, pool inlet jets, scum channels, perimeter draw-off grilles, etc.
Compressed air systems, including compressors (with motors and starters), intercoolers, after-coolers, air storage vessels and receivers, air separators, cooling water systems, lubrication systems, local water coolers, compressed air ancillaries, compressed air connection outlets, instrument air pipeline ancillaries (such as manifolds), instrument air connection outlets, etc.
Vacuum systems, including vacuum pumps, intercoolers and driers, vacuum connection points, etc.
Other specialist piped supply systems.
Pipelines, pipeline ancillaries and fittings.
Air duct lines, duct line ancillaries and fittings.
Thermal insulation.
Silencers and acoustic treatment.
Control components.
Sundry items.
Testing and commissioning.
Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.
Excluded Items (3)
General-purpose LV power supplies (included in sub-element 5.8.2).
Building management systems and other control systems (included in sub-element 5.12.3).
Builder’s work in connection with services (included in element 5.14).