5.11.3-1
1 Lightning protection installations
Component Information
- Code:
- 5.11.3-1
- Sequence:
- 1
- Unit:
- m2
- Sub-Element:
- 5.11.3 - Lightning protection
1 Lightning protection installations
details of each type of system to be stated.
Component Statistics
Measurement Rules
Included Items
Excluded Items
Measurement Rules (5)
The area measured is the area serviced by the system (i.e. the area of the rooms and circulation spaces that are served by the system, which is not necessarily the total GIFA of the building). The area serviced is measured using the rules of measurement for ascertaining the GIFA.
Where more than one system is employed, the area measured for each system is the area serviced by the system.
Work to existing buildings is to be described and identified separately.
Where the contractor is only responsible for designing specific elements and/or components of the building project (i.e. not the entire building project), contractor-designed work is to be described and identified separately.
The percentage additions for testing and commissioning are to be applied to the total cost of the items comprising the sub-element. A single combined percentage addition can be applied to cover the costs of both testing and commissioning.
Included Items (7)
Bonded steel frames and other tape-based systems.
Finials.
Conductor tapes.
Grounding/earthing.
Sundry items.
Testing and commissioning.
Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.
Excluded Items (2)
Earthing systems (included in sub-element 5.8.6).
Builder’s work in connection with services (included in element 5.14).