5.11.2-1
Sprinklers
Component Information
- Code:
- 5.11.2-1
- Sequence:
- 1
- Unit:
- m2
- Sub-Element:
- 5.11.2 - 2 Fire suppression systems
Sprinklers
details of each type of system to be stated.
Component Statistics
Measurement Rules
Included Items
Excluded Items
Measurement Rules (6)
Where components are to be enumerated, the number of components is to be stated.
The area measured is the area serviced by the system (i.e. the area of the rooms and circulation spaces that are served by the system, which is not necessarily the total GIFA of the building). The area serviced is measured using the rules of measurement for ascertaining the GIFA.
Where more than one system is employed, the area measured for each system is the area serviced by the system.
Work to existing buildings is to be described and identified separately.
Where the contractor is only responsible for designing specific elements and/or components of the building project (i.e. not the entire building project), contractor-designed work is to be described and identified separately.
The percentage additions for testing and commissioning are to be applied to the total cost of the items comprising the sub-element. A single combined percentage addition can be applied to cover the costs of both testing and commissioning.
Included Items (11)
Sprinklers, including reaction and control devices, and sprinkler heads.
Deluge systems, including water storage, reaction and control devices, and deluge discharge nozzles.
Gas firefighting systems, including gas storage cylinders and vessels, gas manifolds and equipment, discharge nozzles, detectors and activators.
Foam firefighting systems, including foam generation equipment, storage vessels, detectors and activators, foam discharge nozzles, etc.
Distribution pipelines, pipeline ancillaries and fittings.
Water tanks and cisterns for firefighting installations.
Thermal insulation.
Control components.
Sundry items.
Testing and commissioning.
Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.
Excluded Items (7)
Water supply (included in element 5.4, as appropriate).
General-purpose LV power supplies (included in sub-element 5.8.2).
Fire hydrants (included in sub-element 5.4.1).
Hand-held firefighting equipment, including fire extinguishers, fire blankets, etc. (included in sub-element 4.1.1).
Fire detection and alarm systems (included in sub-element 5.12.1).
Building management systems and other control systems (included in sub-element 5.12.3).
Builder’s work in connection with services (included in element 5.14).