2.2.1-5

Suspended floor slab (Precast/composite decking systems)

Unit: m2 Sub-Element: 2.2.1 - 1 Floors
Component Information
Code:
2.2.1-5
Sequence:
5
Unit:
m2
Sub-Element:
2.2.1 - 1 Floors
Description:

Suspended floor slab (Precast/composite decking systems)

Details to State:

details, including type, thickness (mm), span (m) and loading (kN/m2), to be stated

Component Statistics
7
Measurement Rules
15
Included Items
15
Excluded Items
Measurement Rules (7)
C1 1

The area measured is the surface area of the floor slab. No deduction is to be made for voids within the floor slab that are less than 1.00m2 in surface area.

C2 2

Where more than one floor construction type is employed, the area measured for each floor construction type is measured separately.

C3 3

Where more than one floor construction type is employed, the combined area of each floor construction type should equal the total area of the upper floors.

C4 4

Areas for balconies, galleries, tiered terraces, walkways, internal bridges, external links and roofs to internal buildings should be shown separately.

C5 5

Sloping surfaces to be measured flat on plan.

C6 6

Work to existing buildings is to be described and identified separately.

C7 7

Where the contractor is only responsible for designing specific elements and/or components of the building project, contractor-designed work is to be described and identified separately.

Note: i.e. not the entire building project
Included Items (15)
1.

Suspended floors, including: upper floors; podium slabs forming roofs to basements; balconies (internal and external) that are an integral part of the suspended floor construction; mezzanine floors; service floors; galleries, tiered terraces; walkways, internal bridges; external corridors/bridges forming links between buildings, including supporting frames; roofs to internal buildings, where an integral part of the upper floor construction.

2.

Solid, hollow, tee or other section of precast and prestressed concrete plank and slab decks.

3.

Composite decks of precast and prestressed concrete beams with filler blocks of precast concrete, in situ concrete and other materials.

4.

Composite decks of in situ concrete on precast or prestressed concrete planks.

5.

Hollow tile decks of in situ concrete with filler blocks of clay, precast concrete or other material.

6.

Precast and prestressed concrete components.

7.

In situ concrete.

8.

Site-fixed formwork and reinforcement.

9.

Filler units.

10.

Fixing slips, metal clips and other fixings.

11.

Joints, including grouting joints.

12.

Worked finishes (i.e. in situ surface treatments), including the application of surface hardeners.

13.

Performance tests.

14.

Sundry items.

15.

Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.

Excluded Items (15)
1. Ref: 1.1.3

Precast/composite decking systems used in ground floor construction (included in sub-element 1.1.3).

2. Ref: 2.1.6

Precast decking forming an integral part of precast concrete frame assemblies (included in sub-element 2.1.6).

3. Ref: 2.3

Basement roofs, i.e. where not acting as a podium slab or transfer slab (included in element 2.3).

4. Ref: 2.2.1.7

Non-structural screeds (included in component 2.2.1.7).

5. Ref: 2.2.1.7,2.3.1

Structural screeds (included in component 2.2.1.7 or sub-element 2.3.1, as appropriate).

6. Ref: 3.2.1

Hardeners and sealers applied to suspended floor slabs after construction (included in sub-element 3.2.1).

7. Ref: 3.2.1

Floating floors (included in sub-element 3.2.1).

8. Ref: 3.2.1

Applied floor finishes (included in sub-element 3.2.1).

9. Ref: 3.2.2

Raised access floors (included in sub-element 3.2.2).

10. Ref: 3.3.1

Applied ceiling finishes (included in sub-element 3.3.1).

11. Ref: 3.3.2

False ceilings (included in sub-element 3.3.2).

12. Ref: 3.3.3

Suspended ceilings (included in sub-element 3.3.3).

13. Ref: 3.3.3

Roofs to internal buildings that are not an integral part of the upper floor construction (included in sub-element 3.3.3).

14. Ref: 2.2.2

Balconies that are not an integral part of the upper floor construction (included in sub-element 2.2.2).

15. Ref: 2.2.3

Drainage to balconies that are an integral part of the upper floor construction (included in sub-element 2.2.3).