0.5.1-1
Temporary diversion of drains
Component Information
- Code:
- 0.5.1-1
- Sequence:
- 1
- Unit:
- item
- Sub-Element:
- 0.5.1 - Temporary diversion works
Temporary diversion of drains
details to be stated
Component Statistics
Measurement Rules
Included Items
Excluded Items
Measurement Rules (2)
Works are to be itemised and described.
Where insufficient information is available, such works are to be included in group element 13,as appropriate.
Included Items (6)
All works in connection with temporary diversion of drains.
All works in connection with temporary diversion of services (e.g. water, electricity, gas and communications).
All works in connection with temporary diversion of rivers, streams, etc.
Statutory undertaker’s fees and charges in connection with diversion works.
Sundry items.
Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.
Navigation
Export
API Access
Access this component data programmatically:
GET /api/components/0.5.1/1/- Complete component details