0.5.1-1

Temporary diversion of drains

Unit: item Sub-Element: 0.5.1 - Temporary diversion works
Component Information
Code:
0.5.1-1
Sequence:
1
Unit:
item
Sub-Element:
0.5.1 - Temporary diversion works
Description:

Temporary diversion of drains

Details to State:

details to be stated

Component Statistics
2
Measurement Rules
6
Included Items
0
Excluded Items
Measurement Rules (2)
C1 1

Works are to be itemised and described.

C2 2

Where insufficient information is available, such works are to be included in group element 13,as appropriate.

Included Items (6)
1.

All works in connection with temporary diversion of drains.

2.

All works in connection with temporary diversion of services (e.g. water, electricity, gas and communications).

3.

All works in connection with temporary diversion of rivers, streams, etc.

4.

Statutory undertaker’s fees and charges in connection with diversion works.

5.

Sundry items.

6.

Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.