0.2.2-1

Preparatory to demolition

Unit: item/m2 Sub-Element: 0.2.2 - Soft strip works
Component Information
Code:
0.2.2-1
Sequence:
1
Unit:
item/m2
Sub-Element:
0.2.2 - Soft strip works
Description:

Preparatory to demolition

Details to State:

: extent of works to be stated

Component Statistics
1
Measurement Rules
12
Included Items
1
Excluded Items
Measurement Rules (1)
C1 1

The area measured is the GIFA.

Included Items (12)
1.

Soft strip works carried out separately from demolition works.

2.

Removal of existing non-structural walls and partitions.

3.

Removal of existing internal doors, screens, balustrades, handrails, etc

4.

Removal of finishes.

5.

Removal of furnishings, fixtures and fittings.

6.

Isolating, draining down and disconnecting existing mains services, including water, gas, electricity, drainage, district heating, telecommunication systems, data systems, etc.

7.

Removal of building engineering services, including lift installations.

8.

Credits for materials arising from demolition works.

9.

Disposal of materials arising from soft strip works.

10.

Statutory undertaker’s fees and sundry items.

11.

Charges for disconnecting mains services.

12.

Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.

Excluded Items (1)
1. Ref: 0.1.1

Removal of toxic or hazardous parts of building fabric (e.g. asbestos-containing materials), including materials and chemicals (included in sub-element 0.1.1).