0.1.2-1

Contaminated ground material removal

Unit: m2/m3 Sub-Element: 0.1.2 - Contaminated land
Component Information
Code:
0.1.2-1
Sequence:
1
Unit:
m2/m3
Sub-Element:
0.1.2 - Contaminated land
Description:

Contaminated ground material removal

Details to State:

details to be stated

Component Statistics
4
Measurement Rules
3
Included Items
4
Excluded Items
Measurement Rules (4)
C1 1

The area measured is the area of contaminated land

C2 2

Where the volume of excavation and disposal of contaminated ground material is measured, the volume measured is the surface area of the contaminated material multiplied by the average depth of the contaminated materia

C3 3

Quantities given for disposal of contaminated ground material are the bulk before excavating, and no allowance is made for subsequent variations to bulk or for extra space to accommodate earthwork support

C4 4

Other cost-significant components are to be described and identified separately. Such components are to be measured by area (m2) or linear measurement (m), or enumerated (nr) separately

Included Items (3)
1.

Contaminated ground material removal using dig and dump strategy, including safe disposal of excavated material to licensed tip (non-hazardous and hazardous material), tipping charges and landfill tax.

2.

Contaminated ground material treatment using in situ methods, such as: • dilution • clean cover • on-site encapsulation • bioremediation • soil washing • soil flushing • thermal treatment • vacuum extraction • stabilisation.

3.

Where works are to be carried out by a subcontractor, the subcontractor’s preliminaries, design fees, risk allowance, overheads and profit, with allowance for these to be made within unit rate applied to element or component.

Excluded Items (4)
1. Ref: 11

Undertaking environmental audits and intrusive ground investigations/surveys (included in group element 11).

2. Ref: 11

Preparing remediation strategy/plan (included in group element 11).

3. Ref: 11

Supervision to ensure compliance with remediation strategy/plan (included in group element 11).

4. Ref: 1,8

Reinstatement works required by alleviation strategy (included in group element 1 or group element 8 as appropriate).

Export
View as JSON
API Access

Access this component data programmatically: